Thursday, 24 September 2009

Week 10 - 21 to 25 September 2009

Well, it's started moving again. Funding has been secured and builder given the green light. This week (23rd) the bison floor slabs arrived a lot earlier than expected and were put into place on the ground floor and garage. An early start as first lorry arrived at 0710 hrs according to our on site security guards and chief updater by text - Mark and Michelle. Head of secutity and Lord of Ard development (otherwise known as Sir Trevor) reported further deliveries in the afternoon (not expected until next day). So by end of day all were in place.
Hopefully bricks and block will be delivered next and builder hoping to have brick layers on site by Tuesday.
That's all for this week.